Transmission Line Projects

List of transmission line projects

Transmission Line Projects

Current Projects:
Contract will expand the high voltage power system from the Pul-e-Alam Substation in Logar Province and the Charikar substation in Parwan Province to new substations located in Panjshir Province, Kapisa province and Paktiya Province. This new power system, high voltage transmission lines and substations, will provide electricity to unserved population centers, provide a backbone for a national grid and allow for future expansion of this power grid. The objective of this project is to provide a cost effective, reliable transmission system for the distribution of electric power in Afghanistan to areas such as Panjshir, Kapisa and Paktiya.

Logar- Gardiz 220KV Transmission Line:
Single circuit 220 kV electrical transmission system about 60KM and will deliver power from Pul-Alam Substation located in Pul-e-Alam, Logar to a new substation, Gardez Substation, located in Gardez, Paktiya. The transmission system towers to support two 220 kV transmission circuits.

Gardiz 220/20KV Substation:
Gardez substation have one 220 kV line bay, 20 kV yard with indoor switchgear, two 20 kV line bays each capable of expansion to 34 MVA, line dead-end structures for connection to four 20 kV distribution lines. One high voltage 220 kV/20 kV 16 MVA transformer. Substation designs include a control building utilizing the OPGW for SCADA/EMS. The control building have DABS industry standard bus, transformers, breakers, and line protection. It has been sized and equipped with panels to allow expansion as indicated for substation line bays.

Jabul Seraj-Gulbahar 220KV Transmission Line:
Single circuit 220 kV electrical transmission system is delivering power from Charikar Substation located in Charikar, Parwan to a new substation, Gul Bahar Substation, located in Gul Bahar, Kapisa. The transmission system towers is supporting two 220 kV transmission circuits.

Gulbahar 220/110/20KV Substation:
Gul Bahar substation will serve the area of Gul Bahar and is a junction point for high voltage transmission to other substations located in Panjshir and Kapisa Provinces.
Gul Bahar substation have one 220 kV line bay and two 110 kV line bays. The 220 kV line bay will be used for the connection to the new single circuit transmission system from Charikar Substation. The 110 kV line bays will be used for distribution to a new substation located in Bazarak, Panjshir and an additional 110 kV line bay for distribution to a new substation, located in Nejrab, Kapisa. It has a 20 kV yard with indoor switchgear, connection to two 220 kV/20 kV transformersrated 16 MVA each, and four 20 kV line bays each capable of expansion to 34 MVA. The 20 kV line bays will be designed and installed. It has two 220 kV/110 kV autotransformer for distribution to other substations rated 160 MVA each. Substation designs include a control building utilizing the OPGW for SCADA/EMS. The control building include DABS industry standard bus, transformers, breakers, and line protection. It has been sized and equipped with panels to allow expansion as indicated for substation line bays.

Gulbahar- Nijrab 110KV Transmission Line:
Single circuit 110 kV electrical transmission system is delivering power from Gul Bahar Substation located in Gul Bahar, Kapisa to a new substation being built by others, Nejrab Substation, located in Nejrab, Kapisa.